Quote:
Originally Posted by dowlingm
I seem to remember some chat that Clonmel-Limerick Junction was going to be upgraded to auto level crossings so that routine Sunday operation without crossing staff would be possible. Is that still the plan?
|
7 day operation is perfectly possibly by employing an extra person for each 6 level crossings. That person then provides relief operation to each of the gate keepers on specific days.
Level crossing 1 - Monday
Level crossing 2 - Tueday
Level crossing 3 - Wednesday
Level crossing 4 - Thursday
Level crossing 5 - Friday
Level crossing 6 - Saturday
3-4 additional staff would be required.