I know these are for the signalling upgrade and planned use of GCD as a terminus for Maynooth services, but they seem to be completely rebuilding the platform and trackbed on the 3rd platform - anyone know what the plan is?

GCD could really use better access from the street - I don't use the station myself but there seems to be serious congestion on the bridge everytime a train pulls in.
The third (unused platform) will ultimately become the northbound through platform.

The existing northbound platform will become a turnback platform for terminating services.

There will have to be a remodelling of all the tracks in the area.