08-06-2016, 21:15 | #21 |
Really Really Regluar Poster
Join Date: Jun 2010
Posts: 2,146
|
While it's slightly longer than I would of expected you have to considered the sheer difference in progress at both junctions. Keeping buses running through Abby St junction is really impacting on progress and holding it up.
They are also doing all the electrification works and likely a few days for commissioning the new signal layout. |
09-06-2016, 08:07 | #22 | |
Really Regular Poster
Join Date: Oct 2010
Posts: 951
|
Quote:
It is obvious that good progress is being made with the modified trackwork now substantially in place. Signalling and overhead changes are very modest and hardly likely to add significantly to the closure given the uncomplicated nature of these systems on a tramway - the only urgent change would be to ensure that the facing points approaching the Abbey Street stop are detected. One thing that has been very noticeable in recent years on the big railway is that works which would traditionally have been considered minor and not meriting a line closure are now considered to be major and justification for extended line closures. The renewal of the Tolka Bridge at East Wall a few years ago resulted in more line closures and disruption than did the original DART construction. On one occasion the line north of Connolly, was closed for an entire weekend to remove a turnout into Fairview depot thus gratuitously disrupting tens of thousands of passengers for the most trivial piece of work. Many works now appear to be planned with extensive padding to ensure that it is almost impossible to over-run even if this means that the line remain closed long after the job has finished and everybody has gone home ! |
|
09-06-2016, 16:09 | #23 |
Really Really Regluar Poster
Join Date: Aug 2009
Location: Sligo Line
Posts: 1,115
|
To be fair, this is not just limited to rail infrastructure. The OPW have had a 1 km stretch of the quay walls in Dublin cordoned off for nearly two years so that they can build a one metre high flood barrier. You frequently see road-closures on major roads stretching for weeks or months while they replace sections of bridges.
Modern project planning in Ireland does not appear to have minimisation of public disruption high on the list of priorities for design criteria. Like everything in engineering (civil or otherwise), minimising disruption has a cost and can usually be achieved if the customer demands it. This cost does not seem to be something that the NTA or whatever other public body is willing to bear so instead the passenger ends up paying for it in delays. |
24-06-2016, 17:28 | #24 | |
Local Liaison Officer
Join Date: Dec 2006
Posts: 5,442
|
.
Quote:
__________________
|
|
25-06-2016, 07:41 | #25 |
Really Regular Poster
Join Date: Oct 2010
Posts: 951
|
Works already substantially completed at Abbey Street/O'Connell Street and Abbey Street/ Marlborough Street.
|
28-06-2016, 03:10 | #26 |
Really Really Regluar Poster
Join Date: Aug 2006
Location: Toronto, Canada
Posts: 1,371
|
Here in Toronto the tramway used to be laid in a very basic fashion but it got hammered by use especially by the post-PCC trams. Now the concrete is laid in layers and rubber pads used for vibration reduction. Slower to do but lasts longer.
https://youtu.be/kPJuU8CaKAc |
28-06-2016, 08:16 | #27 |
Really Regular Poster
Join Date: Oct 2010
Posts: 951
|
Re-opens July 3rd.
|
28-06-2016, 11:52 | #28 |
Member
Join Date: Dec 2005
Location: Drogheda, Ireland
Posts: 1,275
|
I think the RPA and contractors can be congratulations for getting the job done reasonably quickly and the line reopened early. I still think they could have managed the replacement bus service better, and I suspect most people found it easier to just walk during the closure, but things did run reasonably smoothly apart from that.
James |
28-06-2016, 15:25 | #29 |
Really Regular Poster
Join Date: Oct 2007
Posts: 279
|
Am I the only person who thinks they massively inflated the time needed in public information to make themselves look good with " an early finish" ?
__________________
26271 12-60 |
29-06-2016, 14:19 | #30 | |
Member
Join Date: Dec 2005
Location: Drogheda, Ireland
Posts: 1,275
|
Quote:
Basically, it would be irresponsible not to allow some reasonable contingency in the project schedule. James |
|
29-06-2016, 16:52 | #31 | |
Really Regular Poster
Join Date: Aug 2013
Posts: 602
|
Quote:
The lesson from Harcourt St has been learnt - works over-ran significantly there due to the plans of the utility layout bearing no resemblance to reality. Far better to build in extra time lest anything similar happens again. |
|
29-06-2016, 20:26 | #32 |
Really Regular Poster
Join Date: Oct 2010
Posts: 951
|
I have a degree of sympathy with both viewpoints, it is reasonable and proper to have contingency. I stress I don't know in sufficient detail what was involved in the LUAS works and would not therefore be competent to judge the degree of padding in the time announced as being required to complete the task.
I do know of other infrastructure works where operator convenience has trumped the legitimate needs of the public and where grossly excessive time has been allowed for very minor works. Last edited by Inniskeen : 29-06-2016 at 20:30. |