Quote:
Originally Posted by Mark Gleeson View Post
The speed limits are due to numerous level crossings with substandard sighting distances due in part vertical and horizontal curvature. Absolutely no discretion or exemptions are allowed as this is considered a new route.

The line was never built for passenger services and combined with a very boggy foundation has serious restrictions.

The line was reopened on the cheap to keep politicians happy, the consultants report looked at basically a new line from Limerick to Oranmore but came back at 600 million to 1 billion depending on spec/route.
So I am assuming there are no plans to bring this line up to a more suitable level? Also if the line was not intended for passenger services, what was it intended for? There are no heavy industries on that line. And to me it seems like the bad shape of the infrastructure will pretty much result in no one taking the whole route to Galway and instead opt for faster bus services.
LlewellynJones is offline   Reply With Quote
Unread 08-05-2012, 13:12   #2
Mark Gleeson
Technical Officer
 
Mark Gleeson's Avatar
 
Join Date: Dec 2005
Location: Coach C, Seat 33
Posts: 12,669
Default

The line was opened solely to shut up some politicians and local interests who were under the impression the line would be some kind of amazing solution to the west of Ireland's problems. It failed miserably to meet the very low passenger number targets.

The solution chosen by Government was the cheapest possible option to reopen the line, the fanciful 1 billion for a new line were ruled out. All investment proposals for the line where investigated and ALL failed to meet the minimum standard to justify investment, despite this the line was reopened

The line was originally built on the cheap in the Victorian era to transport cattle and sugar beet.

In order to make up the massive operating loss as a result of the line opening the Waterford Rosslare line which carried 3 times more passengers per train than Ennis - Athenry was axed.
Mark Gleeson is offline   Reply With Quote
Unread 08-05-2012, 18:50   #3
doherty jack
Regular Poster
 
Join Date: Feb 2012
Location: Roscrea
Posts: 89
Default

the thing about Waterford/rosslare was the population wasnt big enough for starters plus trains were ran at peak commuting times and often ran empty !

i agree little or no promotion was done on it , connections at each end should been better

also the speeds on the line were quite good!
doherty jack is offline   Reply With Quote
Unread 08-05-2012, 18:53   #4
Mark Gleeson
Technical Officer
 
Mark Gleeson's Avatar
 
Join Date: Dec 2005
Location: Coach C, Seat 33
Posts: 12,669
Default

Waterford Rosslare had an average load of 20+ per train, 30-40 minutes faster than car

Ennis - Athenry is currently averaging 7, 30-40 minutes slower than car
Mark Gleeson is offline   Reply With Quote
Unread 08-05-2012, 19:14   #5
doherty jack
Regular Poster
 
Join Date: Feb 2012
Location: Roscrea
Posts: 89
Default

ive been on that train more than 10 times isnt alot at stages i was the only person on-board and there was never over 15 when i was on -board.....
doherty jack is offline   Reply With Quote
Unread 13-05-2012, 14:26   #6
Mark Gleeson
Technical Officer
 
Mark Gleeson's Avatar
 
Join Date: Dec 2005
Location: Coach C, Seat 33
Posts: 12,669
Default

Just to prove how crazy up and down, left right the WRC is

http://www.flickr.com/photos/finnyus...57629698779844

http://www.flickr.com/photos/finnyus...7629698779844/

This has a massive impact on sighting distance and train performance and imposes unavoidable speed limits

Last edited by Mark Gleeson : 13-05-2012 at 14:29.
Mark Gleeson is offline   Reply With Quote
Unread 18-05-2012, 20:37   #7
ccos
Member
 
ccos's Avatar
 
Join Date: May 2006
Location: Kazbegi
Posts: 281
Default

For what its worth, I think its time to end the argument about the Ennis-Athenry line, for better or worse the boat on its reopening has long sailed.
Are the few people who use the route now rail users or not and have they no less right to be represented by the RUI.
Its all well and good saying I told u so but the line is open and now the focus must be on getting it to work.

First, there seems to be a fixation in Ireland with line speed vs cars, in my experience people with cars (unless commuting into a city centre) would rather eat their hat then use a train, when visiting friends in Ennis they always offer to drive to Limerick, thinking I'd have to be daft to get the train. I use trains because I have no car but like to move around.
There are in my experience 3 things this or any other line in Ireland needs to boost numbers and attract passengers.
1. More services, people, especially young people like the idea of turning up whenever and getting a train wherever, do you think the DART would carry 10% of its current passngers with only 10% of the services. All routes should have an hourly service, especially now we have railcars.
Connections, If I travel Waterford Limerick I have to wait a long time in Lmk Jctn for a train ???? The Dublin Galway train should connect nicely with the Athenry-Ennis service, they want to stop the Limerick Nenagh service, the last time I was tried to get it my Train from Ennis( the first for two hours) missed it by a matter of minutes. Time trains to arrive at junctions together and leave together. Try to go Cobh- Midleton, it takes over an hour outside peak.
Trains. Commuter sets are not ideal for Waterford Galway, its not as if they need the Density, Train Travel on 2200s or mark 4 is so much more comfartable, couldnt some railcars be modified for "regional work" to have a better set up for this route.

Last edited by ccos : 18-05-2012 at 20:39.
ccos is offline   Reply With Quote
Reply


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

vB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Forum Jump


All times are GMT. The time now is 07:16.


Powered by vBulletin
Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.